30x40 site house construction cost (Ground + 1, 3 BHK) up to 1875 Sqft built-up area.

1. Using solid concrete blocks for construction.

Materials RequiredQtyStandard QualityPremium Quality
TMT Steel Bars74,76,000 ( 68000 / tons)5,46,000 ( 78000 / tons)
Cement7162,61,340 ( 365 / bags)3,04,300 ( 425 / bags)
Plastering M Sand1181,41,600 ( 1200 / tons)1,65,200 ( 1400 / tons)
Concrete M Sand5239,000 ( 750 / tons)49,400 ( 950 / tons)
40mm Jelly2015,000 ( 750 / tons)17,000 ( 850 / tons)
20mm Jelly12090,000 ( 750 / tons)1,02,000 ( 850 / tons)
6" Concrete Block2,40084,000 ( 35 / blocks)1,08,000 ( 45 / blocks)
4" Concrete Block80024,000 ( 30 / blocks)28,000 ( 35 / blocks)
Materials Cost (Rs.) for 1875 Sqft11,30,940 @ 603 / sft13,19,900 @ 704 / sft
Labor Cost (Rs.) for 1875 Sqft5,62,500 @ 300 / sft6,18,750 @ 330 / sft
Total Construction Cost (Rs.)16,93,440 @ 903 / sft19,38,650 @ 1034 / sft

Using wirecut clay bricks for construction.

Materials RequiredQtyStandard QualityPremium Quality
TMT Steel Bars74,76,000 ( 68000 / tons)5,46,000 ( 78000 / tons)
Cement7192,62,435 ( 365 / bags)3,05,575 ( 425 / bags)
Plastering M Sand1181,41,600 ( 1200 / tons)1,65,200 ( 1400 / tons)
Concrete M Sand5239,000 ( 750 / tons)49,400 ( 950 / tons)
40mm Jelly2015,000 ( 750 / tons)17,000 ( 850 / tons)
20mm Jelly12090,000 ( 750 / tons)1,02,000 ( 850 / tons)
Clay Bricks (4")162001,62,000 ( 10 / bricks)2,26,800 ( 14 / bricks)
Materials Cost (Rs.) for 1875 sqft11,86,035 @ 633 / sft14,11,975 @ 753 / sft
Labor Cost (Rs.) for 1875 sqft6,18,750 @ 330 / sft6,56,250 @ 350 / sft
Total Construction Cost (Rs.)18,04,785 @ 963 / sft20,68,225 @ 1103 / sft

Note:

1. Above mentioned prices are for the foundation superstructure only.

2. Above mentioned quantity is approximate and depends on the actual design.

3. Finishes like electrical, plumbing, flooring, windows, fabrication, painting, etc ..are not included.

4. Prices are subject to change. Rates were last updated on 4th March 2023.