1. With Concrete Blocks
Materials Required | QTY | Unit | Premium | Standard |
---|---|---|---|---|
TMT Steel | 7 | Tonnes | ₹3,29,000 | ₹3,03,100 |
Cement | 716 | Bags | ₹2,59,908 | ₹2,44,156 |
Plastering M Sand | 118 | Tonnes | ₹1,65,200 | ₹1,53,400 |
Concrete M Sand | 52 | Tonnes | ₹49,400 | ₹41,600 |
40mm Jelly | 410 | Cft | ₹10,250 | ₹9,430 |
20mm Jelly | 2305 | Cft | ₹57,625 | ₹53,015 |
6" Concrete Block | 2400 | Blocks | ₹1,20,000 | ₹76,800 |
4" Concrete Block | 800 | Blocks | ₹28,800 | ₹20,000 |
Total: | ₹10,20,183 | ₹9,01,501 |
2. With Clay Bricks
Materials Required | QTY | Unit | Premium | Standard |
---|---|---|---|---|
TMT Steel | 7 | Tonnes | ₹3,29,000 | ₹3,03,100 |
Cement | 716 | Bags | ₹2,59,908 | ₹2,44,156 |
Plastering M Sand | 118 | Tonnes | ₹1,65,200 | ₹1,53,400 |
Concrete M Sand | 52 | Tonnes | ₹49,400 | ₹41,600 |
40mm Jelly | 410 | Cft | ₹10,250 | ₹9,430 |
20mm Jelly | 2305 | Cft | ₹57,625 | ₹53,015 |
4" Clay Bricks | 16200 | Nos. | ₹1,13,400 | ₹97,200 |
Total: | ₹9,84,783 | ₹9,01,901 |
1. Above mentioned prices are for foundation superstructure only.
2. Above mentioned quantity is approximate and depends on the actual design.
3. Labour, electricity, plumbing, painting & finishes cost are not included.
4. Prices are subjected to change. Rates last updated on 21st January 2019.